LISTING · TRS315CSTN · ALUMINIUM TENT HALL FOR REUSE

Used aluminium tent hall 15 × 21 m with sandwich walls and two roller doors

An aluminium tent hall of system F30 with a 15.00 m clear span and 21.00 m length – 315 m² on the grid. The roof is a white PVC membrane, the walls are 40 mm sandwich panels. Two roller doors with controls, a personnel door and the type structural calculation are included. The hall is standing and will be dismantled by arrangement.

Johann Thal · THAL REUSE SYSTEMS · 09/11/2026

TRS315CSTN – Isometric view of the structure based on the building documents – schematic, not a photograph.
Isometric view of the structure based on the building documents – schematic, not a photograph.
15.00 mclear span, 5 aluminium frames
315 m²grid 15.00 × 21.00 m
6.12 / 8.61 mside height / ridge above base
2 roller doors4.00 × 4.20 and 4.85 × 4.65 m
Sandwich 40 mmwalls · PVC membrane roof
by arrangementavailability · price on request

Location, complete building documents and a viewing date are provided after a short qualification and signature of the THAL REUSE STANDARD Fair Use Agreement (TRS-FA).

Hall passport · issued 09/11/2026
TRS315CSTN

Identification

Object ID
TRS315CSTN
Long form
TRS-315-CSTN-W15L21-01
Type
aluminium tent hall, system F30
Designation
storage tent with solid walls, gable roof
Passport no.
HP-20261109-01
Location
exact location after qualification

Origin and documents

System
temporary structure to EN 13782
Type calculation
tent type F30, 252 pages, spans 15–30 m
Drawings
floor plan and elevations 1:100
Use
storage hall
Inspection log
being requested

Geometry

Grid
15.00 × 21.00 m (basis of object ID)
External
15.33 × 21.12 m
Bays
4 bays: 5.00 / 5.00 / 5.00 / 6.00 m
Heights
base 0.67 m · side height 6.12 m · ridge 8.61 m above base
Roof pitch
approx. 18°

Structure

Frames
5 two-hinged aluminium frames, clear span
Material
EN AW-6082 T6, steel parts S235/S355
Gables
2 gable posts each, 5.00 m grid
Bracing
roof bracing (cables)
Connections
plugged and bolted, for repeated erection

Envelope and equipment

Roof
white PVC membrane
Walls
40 mm sandwich panels
Doors
roller door 4.00 × 4.20 m (gable) · roller door 4.85 × 4.65 m (long side), with controls
Door
1 personnel door
Drainage
box gutters

Terms

Price
on request after qualification
Availability
by arrangement
Scope
structure, envelope and doors, ex site
Not included
base, foundations, groundwork at the new site
Dismantling
by the buyer or via our partner network

A tent hall with solid walls

The structure is a proven aluminium tent system: five two-hinged frames at bay widths of 5.00 / 5.00 / 5.00 / 6.00 m carry a gable roof at about 18°. Instead of side tarpaulins the hall has sandwich panel walls – more robust, lockable and more comfortable in use than a pure tarpaulin tent.

  • Clear span: 15.00 m free span for forklifts, trucks and storage.
  • High: 6.12 m side height on a 0.67 m base.
  • Demountable: tent systems are designed for repeated erection; all connections can be released.

Dimensions on all reference levels

The object ID is derived from the grid dimension. External size and heights matter for the plot and the foundations.

ReferenceValueNote
Grid (system)15.00 × 21.00 m315 m², basis of the object ID
External15.33 × 21.12 mspace required on the plot
Clear internal14.66 × 20.88 musable floor area
Side height / ridge6.12 / 8.61 mabove top of base
Base0.67 mexisting, not included

Structure: aluminium system F30

The frames are made of aluminium EN AW-6082 T6, knee braces and connection parts of steel. Two gable posts per gable at a 5.00 m grid carry the wall and the roller door. Roof bracing stiffens the hall longitudinally. Purlin and bracing positions in the drawings are schematic. The drawings are labelled in German.

TRS315CSTN – Sheet 05: isometric view of the structure with main dimensions – schematic.
Sheet 05: isometric view of the structure with main dimensions – schematic.
TRS315CSTN – Sheet 02: cross-section of the main frame – span, base, side height, ridge.
Sheet 02: cross-section of the main frame – span, base, side height, ridge.

Floor plan and elevations

In one end bay a corner of about 5 × 5 m is roofed but separated from the interior by walls. When re-erected, this corner can be closed or omitted.

TRS315CSTN – Sheet 01: grid and column plan with doors and inner corner.
Sheet 01: grid and column plan with doors and inner corner.
TRS315CSTN – Sheet 02b: gable elevation axis 1 with gable posts and roller door.
Sheet 02b: gable elevation axis 1 with gable posts and roller door.
TRS315CSTN – Sheet 03: long elevation with bays, roller door and personnel door.
Sheet 03: long elevation with bays, roller door and personnel door.

Structural calculation and range of application (indicative)

The hall comes with the F30 type structural calculation for a temporary structure to EN 13782. It covers spans of 15 to 30 m with 3 m and 4 m side heights and applies no snow load – in snowfall the tent must be heated permanently. The executed side height of 6.12 m is not covered. Two routes are available for re-erection: reverting to the verified 4 m side-height variant, or a new structural verification.

ActionSituationBasisAssessment
Snowheated operation (≥ 2 °C)EN 13782, type calculationwithin the type calculation (side height ≤ 4 m)
Snowunheated, all yeartype calculation without snow loadnew verification, strengthening likely
Windv_ref ≤ 28 m/s, side height ≤ 4 mstandard loads EN 13782within the type calculation
Windside height 6.12 m–new verification required

The information on the range of application and on possible strengthening measures is an indicative assessment based on the available documents. It does not replace a structural calculation. THAL REUSE SYSTEMS accepts no liability for it. Suitability for a specific site and the type and extent of any strengthening must be verified by a structural engineer appointed by the buyer.

Suitable second uses

Storage for materials, machinery and bulk goods; weather-protection and transhipment hall; seasonal storage in agriculture, trade and logistics; heated production or assembly hall. The clear span and large doors allow forklift traffic and truck access.

Dismantling and re-erection

  1. Dismantling: remove doors and electrics, take off the membrane, dismantle and stack the sandwich panels.
  2. Marking: label frames, gable posts, purlins and bracing by axis and position.
  3. Loading: short, light aluminium profiles – probably no special transport needed.
  4. Re-erection: verification for the chosen side height, anchorage or foundations at the new site, inspection as a temporary structure if applicable.

For planning and permits at the new site we hand over the type calculation and drawings. On request our partner network handles dismantling, marking and loading.

Frequently asked questions

What does the hall cost? We quote the price on request after a short qualification.

When is the hall available? Availability is agreed with you – dismantling and collection by arrangement.

Is there a structural calculation? Yes, the F30 type calculation is available. It does not cover the executed 6.12 m side height; this needs a new verification or a reduction to 4 m side height.

Is the hall suitable for winter? The type calculation applies no snow load. Without a new verification the hall suits heated operation or snow-free periods.

Request documents

After qualification you receive the location, exposé, hall passport and building documents. Please quote object ID TRS315CSTN.

Johann Thal · Founder THAL REUSE SYSTEMS
Phone +49 30 80584249 · sales@thalreuse.systems · thalreuse.systems

Want to sell a hall? Talk to us – we buy or find the right buyer through our network. Offer a hall →

All information is based on the building documents, without guarantee; dimensions are approximate. Subject to prior sale. This article does not replace specialist design, structural or permit checks at the new site.